I welcome you all to the 8th Annual General Meeting of your Company.

 It gives me immense pleasure to inform you that the project activities are at their peak and about 73 % physical progress have been achieved as on date. The civil structural works in the Nuclear Island Connected Building have been completed and the finishing works are in progress.

 In the procurement front, the manufacturing of challenging nuclear components like the Steam generators and the Secondary sodium pumps and the Additional Inclined Fuel Transfer Machine (IFTM) were completed and delivered at site. As far as installation is concerned, the two Steam generators were successfully installed in position. The installation of huge diameter critical reactor components like the Thermal baffle, the Integrated Grid plate-Primary Pipe assembly, the Inner vessel and the Roof slab have been completed successfully in this year. The installation of four Diesel Generator sets has been completed. The Installation of 6.6 kV switchgear panels and two battery banks has been completed.  

The pre-commissioning activities for the raw water / fire water pump house have started. The High voltage testing of all the 13 bays in the Gas Insulated Switchyard (GIS) have been completed. The testing of the Additional IFTM in air for 50 cycles has been successfully completed at IGCAR.

 The Pre-project activities for FBR 1&2 have commenced. The Geo-technical investigations, bathometry of sea bed, soil investigation, plan layout and the conceptual design of Site Assembly Shop have been completed.

 Harmonious employee relationship has prevailed in the Project.  Not a single man-day was lost due to industrial unrest of any kind.

 Continuous efforts are on to ensure transparency in all dealings. The Company has been responding to all the RTI related queries.

 Your company is conscious of its social obligations and is trying to improve the quality of life of the people residing in the neighborhood by carrying out various social programmes mainly focusing on Health care, Education, Infrastructure and Environment.

 Atomic Energy Commission(AEC) has issued Guideline s inter-alia on Corporate Governance in the year, 2009.  Considering the importance of Corporate Governance, BHAVINI (a nonlisted CPSE) generally complies with the Corporate Governance guidelines issued by AEC.

 I would like to express my gratitude to the Department of Atomic Energy, various other Ministries and Departments of the Government of India, Planning Commission, and Atomic Energy Regulatory Board for their support.  I would also like to place on record the excellent support extended by Indira Gandhi Centre for Atomic Research, Nuclear Power Corporation of India Limited, Bhabha Atomic Research Centre, Nuclear Fuel Complex, Heavy Water Board, Electronics Corporation of India Limited and other units of Department of Atomic Energy in the implementation of PFBR.  I am thankful to the Statutory Auditors, the Comptroller and Auditor General of India for their services and valuable advice.

 I express my sincere thanks to Directors on the Board, each and every employee, supporting industries, consultants and other stakeholders of your Company.

 I now move the Directors’ Report and Audited Accounts for the year 2010-11 for your consideration and adoption.

 

(S.K.Jain)       

     Chairman & Managing Director

Place :  Chennai